responses. Individual names altered for privacy purposes. The information contained in this website is provided for informational purposes only and should not be construed as a forum for customer support requests. Any customer support requests should be directed to the official HCL customer support channels below:
In two weeks we are scheduled to upgrade from 7.0.4 to 8.5.1 FP2. Our production domino servers run on System i V6R1. We are taking the following steps to upgrade (as recommanded by IBM)
1 - Upgrade Domino Administrators' clients to 8.5.1
2 - Upgrade the design of the domino directory to 8.5.1 on the primary server (allow time for the cluster mates to catch up)
3 - Install a new of 8.5.1 server to the existing domino domain (as additional server)
4 - The existing 7.0.4 server will not be upgraded. Users will be migrated to the 8.5.1 server. When all users, services, tasks moved to the new 8.5.1, the existing 7.0.4 server will retire
I'd like to know if we are missing any steps...anything else that we shyould be aware of?...our tests in Windows environment (using this method)have been successful.